Large-Scale Data Centre Development - Piling Works

  • NSW, Australia
  • April - June 2026
  • Civil Construction

BY Group delivered the piling package under a highly compressed programme, installing over 1,500 piles within 30 business days. 

Achieving this rate required significant resourcing and coordination. Nine piling rigs were mobilised across the building pads, supported by 12 crawler cranes and 12 concrete pumps, with the site receiving up to 300 concrete deliveries per day at peak production.

Detailed sequencing, traffic management and supply chain coordination kept every rig productive and maintained continuous concrete supply, allowing the works to be completed within the compressed programme without compromising quality or safety.


Key Highlights:
  • Design finalisation for piling works

  • Liaison with the client’s consultants to complete design

  • Mobilisation and management of nine (9) piling rigs to site

  • Installation of 1,500 piles over a compressed 30-day programme

  • The works utilised nine piling rigs on site, with three rigs on each building pad, and required over 300 concrete truck deliveries per day.

Contact Us

Want to know more about BY Group? We’d love to hear from you. Contact our team today.

CONTACT US

TOP