Full refurbishment of an occupied Police station in multiple stages, including demolition and strip-out, new walls, ceiling and floor finishes, building services and furniture, fittings and equipment (FF&E). External works including hard and soft landscaping and roof repairs.
Key Considerations:
-
Requirement to stage and plan works across multiple work zones.
-
Program Constraints for the Custody Area where delivery must be carried out within 12 weeks of contract execution.
-
Works to be completed on a live Police site.
-
Successful relocation of various Police Units to temporary work space in the First Floor Training room during works in their respective areas.
-
Achieving compliance with relevant Police Department standards.
-
Potential to encounter hazardous materials, such as asbestos, lead base paint, etc.
-
Ability to deliver the project efficiently in the current COVID-19 pandemic environment.